A & B work 5 hours a day and complete work in 2 days. B and C work 5 hours a day and complete the same work in 4 days. A and C work 6 hours a day and complete the same in 2 days. How many days will A take to complete the work if he is working 5 hours a day alone?
A
5
B
12
C
3
D
15
Answer
3
Explanation
Solution
The correct option is (C): 3.