Question
Mathematics Question on Time and Work
A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37/100 of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to comlete the entire work?
25 days
20 days
30 days
40 days
20 days
Solution
A, B, and C together complete the job in 10 days.
∴ Their combined efficiency is (101) of the job per day.
∴ A+B+C worked for the first 3 days and completed (10037) of the job.
After the first 3 days, the remaining work is (1−10037=10063).
A and B complete this remaining work in ( 10 - 3 = 7 ) days.
Therefore, their combined efficiency is (10063÷7=1009) of the job per day.
It is given that,
the work done by A in 5 days is equal to the work done by B in 4 days, [5×Work Rate of A=4×Work Rate of B][Work Rate of BWork Rate of A=54]
Now,
Let the efficiency of A be ( 4x ) and the work rate of B be ( 5x ).
∴ (4x+5x=1009⇒9x=1009⇒x=1001).
efficiency of A is (4x=4×1001=1004=251).
efficiency of B is (5x=5×1001=1005=201).
Hence, B is the fastest worker and can complete the entire job in 20 days.