9 men working together can complete a piece of work in 12 days. How many days will it take for 24 men to complete the same piece of work?

A

2.5 days

B

3.5 days

C

4.5 days

D

5.5 days

Answer

4.5 days

Explanation

Solution

The correct answer is (C): 4.5 days