Question
Quantitative Ability and Data Interpretation Question on Time and Work
3 men and 18 women together take 2 days to complete a piece of work.How many days will 9 women alone take to complete the piece of work,if 6 men alone can complete the piece of work in 3 days?
A
5
B
6
C
7
D
9
Answer
6
Explanation
Solution
The correct option is (B): 6.