Question
Mathematics Question on Sequences and Series
150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.
Let x be the number of days in which 150 workers finish the work.
According to the given information,
150x = 150 + 146 + 142 + …. (x + 8) terms
The series 150 + 146 + 142 + …. (x + 8) terms is an A.P. with first term 146, common difference –4 and number of terms as (x + 8)
⇒150x=2(x+8)[2(150)+(x+8−1)(−4)]
⇒150x=(x+8)[150+(x+7)(−2)]
⇒150x=(x+8)(150−2x−14)
⇒150x=(x+8)(136−2x)
⇒75x=(x+8)(68−x)
⇒75x=68x−x2+544−8x
⇒x2+75x−60x−544=0
⇒x2+15x−544=0
⇒x2+32x−7x−544=0
⇒x(x+32)−17(x+32)=0
⇒(x−17)(x+32)=0
⇒x=17orx=−32
However, x cannot be negative.
∴x=17
Therefore, originally, the number of days in which the work was completed is 17.
Thus, required number of days = (17 + 8) = 25